| |

Q & A - The B2133 Loxwood Crossing

What will it look like?
Construction Pictures of the new lock.
Q Surely we can squeeze enough headroom out of the existing crossing without all the expense of a new lock to the west?
- Devils Hole Lock
- DHL mitre = 18.77 m AOD
- Required depth of water = 1.4 m
- Therefore:-
- Water level below DHL = 20.17 m AOD
- The B2133 Road
- Road Level = 21.74 m AOD
- Road thickness = 0.6 m
- Therefore:-
- Underside of bridge = 21.09 m AOD
- Water level below DHL = 20.17 m AOD
- Therefore:-
- Headroom Available = 0.92 m
- But the required headroom is 2.4 m
- Minimum Headroom Required = 2.4 m
- Headroom Available = 0.92 m
- Therefore:-
- Lift road by 1.48 m
or
- Lower canal by 1.48 m
- Constraints on Lifting the Road
- Maximum brow 1000 m radius
- Maximum valley 500 m radius
- Max permitted Road lift is 0.42 m
- Required Lift 1.48 m
- Therefore:-
- Lifting the road on its own is not enough, the canal has to be lowered as well.
- Lift the Road
- Additional Road Building Costs
- Un-quantifiable Risks
- Typically
Greater disruption of the traffic
- Placating the households on the High Street and the Onslow Arms
- Lower the canal
- Extra costs
- Steel Piling
- Excavation
- All risks quantifiable
- The question was:
- Can enough headroom be squeezed out of the existing crossing?
- The answer:
Q Wouldn't a lifting bridge solve all our problems?
- WSCC will not accept the cost responsibility to service and maintain the bridge or to replace the bridge when required, say after 50 years.
- WACT would be required to give WSCC a bond to the value of replacing the bridge should WACT fail in their responsibilities.
- WACT would have to employ full time staff to service and maintain the lifting bridge for the life of the canal.
- WACT would have to replace the bridge when required.
- Because there is no ready alternative route for emergency vehicles, WACT could well be legally responsible for consequential damages.
- Lifting Bridge Constraints
- COSTS
- Bond immediately doubles cost
- Servicing and replacement over 120 years?
- Legal implications of failure of the bridge to operate or malfunction?
Q Why can't the winding hole stay where it is?
- Filling the winding hole reduces the project costs by £20000.
- Reduced off site spoil disposal
- Reduced bank protection required
- Easier disabled access to walkway under bridge
- Winding hole is too small for boats larger than ZK
Q Why ruin Brewhurst Lock when we have spent so much effort restoring it?
- Yes, but why didn't the Trust get it right first time, as per Halcrow's 1993 Report?
- Brewhurst 1995
- Brewhurst Lock
- A lot of what can be seen is concrete!
- The largest cost £24,800 relates to fitting smaller gates
Q Why don't we avoid Brewhurst Lock altogether and take a low-level route through the car-park?
Q Will WSCC fund the towpath or bridleway under the bridge? No
Q Will the towpath be a permissive right of way? Yes
|
|
 |
 |
 |
 |
 |
 |
BACK
Last updated December 09, 2005
|