|
| |

Restoration
The Loxwood Link Extension
|



Map 7


Barnsill Bridge rebuilt in 1989 joining two short sections dredged a few years earlier.

Baldwin's Knob Lock - restored in 1992.

Brewhurst Lane Bridge - rebuilt in 1994.

Brewhurst Lock - restored in 1996.

Onslow pound - restored in 1998.

And now -

Drungewick Lane Bridge - built 2001 and in use.
|

|
|
|
The Wey & Arun Canal Trust is dedicated to the conservation, preservation
and restoration of the Wey & Arun Canal, 'London's lost route to
the sea' and the Loxwood Link is a stretch of the canal,
restored in the late 1990s.
|
|
|
|
|
|
1 - Onslow Arms, Loxwood
2 - Brewhurst Lock
3 - Brewhurst Lane Bridge
4 - Baldwin's Knob Lock
5 - Barnsill Bridge
6 - Drungewick Lane
7 - River Lox
|
|
|
|
On this stretch volunteers have restored two locks (Baldwin's Knob
Lock, and Brewhurst Lock) and two accommodation bridges (Barnsill
Bridge, and Brewhurst Lane Bridge), for which in 1997 they were
awarded the Royal Institution of Chartered Surveyors Country
and Coastal Regeneration Award, and by the Inland Waterway Association
the Christopher Power Prize for the top restoration group
in the whole of the UK.
|
|
|
|
From near Drungewick Lane to Loxwood this 1 1/2 mile section of the waterway
has been restored to full navigation and the Trust's trip boat Zachariah
Keppel operates on it throughout the season.
| |
|
|
|
|
| |
The stretch of canal from Drungewick Lane to Drungewick Lock, a
distance of half a mile, was dredged and cleared in 1989 by the landowner.
| | |
|
|
The Loxwood Link Extension Project (LLEP) consists of several engineering components which, when completed, will connect these two sections and, subject only to water supply, enable through navigation from the Onslow Arms in Loxwood to Drungewick Lock.
|
|
|

If gates are installed in a lock which is not in use they deteriorate quickly.

Gates in a working lock keep wet and thus last longer.
|

|
|
|
| |
1 - Onslow Arms, Loxwood
2 - Brewhurst Lane Bridge
3 - Baldwin's Knob Lock
4 - Drungewick aqueduct
(site of)
5 - Drungewick Lane
canal bridge (site of)
|
|
|
Connecting with this exciting project these two lengths of this historic waterway will provide many benefits, including - |
|
|
|
-
Enabling boats to navigate a canal last used in 1868.
-
Giving public access, by trip boat, to parts of West Sussex not
previously available.
-
Providing a new access for walkers by the introduction of a
new permissive right of way.
-
Allowing further restoration southwards to Newbridge, converting
from dereliction to a navigable canal, thus providing over six
miles of continuous waterway. Greater bio-diversity, particularly
birds (swans, kingfishers, nightingales) , dragonflies, fish,
flowers.
-
An enhanced tourist feature to the area, particularly for
walkers, bird watchers, fishermen etc.
|
|
|
| The project centres on the much vaunted replacement of Drungewick aqueduct and the removal and replacement of the road bridge in Drungewick Lane. Other elements involve embankments to the aqueduct and to the road bridge, a winding hole, new lock gates, a back-pumping system at the lock, and fencing along the permissive right of way along the towpath.
[drawing: Paul Rippingham]
| |
|
|
|
The extension project is being accomplished in three main stages
-
|
|
|
|
-
August 2000 - Re-instating Drungewick Lane road bridge.
-
Next will be the heavy plant crossing to the gauging station and re-instating the embankments etc.
-
This will then be followed by the final stage - that of building the aqueduct itself.
|
|
|
|
|
|
|
The road bridge at Drungewick Lane
The canal traffic having ceased in 1868, by 1905 the Drungewick
Lane bridge was in such a state of disrepair, that the local authority
was persuaded to remove it.

The closure notice was dated July 3rd 1905.
| |
|
|
|
|
| |
The building of the new bridge at this site is being undertaken solely by contractors under the control and direction of West Sussex County Council, Highways Department.
|
|
| |
Construction work on the new bridge started in August 2000, although some preparatory work began earlier.
[more on the bridge works]
|
|
|
The Aqueduct
The original brick aqueduct was probably built on wooden foundations laid on the clay strata and over the years it experienced some heave and subsidence leading to bad cracking and distortion. It was demolished in 1957 by the river authority to ease flood control. Following its demolition the course of the river was altered and a gauging station introduced.
|
|
|
|
|
|
| |
Josias Jessop's original 1814 "Design for an Aqueduct over the Loxwood River at Drungewick for the Arun & Wey Junction Canal" shows a brick structure with two arches, although the aqueduct as built appears to have had three arches.
However, the Environment Agency (EA) has made a requirement for the aqueduct structure to have an air draft to cope with a worst case flooding in a statistical 100 years period. To meet this requirement and maintain the canal bed at the same level as the original design, with the same materials, is not possible.
|
|
|
|
|
|
|
Therefore, in 1995, Tony Gee & Partners were asked to design an
aqueduct to meet the EA requirements. As part of those requirements,
a constraint was made that the construction should take place only
between April and September, because of the risk of flooding of
the works during the winter months.
| |  |
|
|
| Embankments to the aqueduct and bridge
The embankments for the aqueduct will connect the canal as it is
now, to the abutments of the newly constructed aqueduct.
|
|
|
|
 |
|
1 - new embankments
2 - new Drungewick Aqueduct
3 - new Drungewick Lane bridge
4 - Gauging station
5 - River Lox
|
|
|
|
As the surface level of the field is approximately the same as that of the constructed canal, the embankment will be simply the placement of clay to form the canal banks, rolled into place, which is in effect the same method to that used when the canal was originally built.
Similar embankments will be required to connect the aqueduct and bridge structures.
| |
|
|
|
|
 |
|
The EA has required that provision for access by heavy vehicles to its gauging station be made. This will be constructed in this embankment, and concrete planks, to be fitted across the canal when required, normally being stored locally enabling free passage down the waterway.
| |
|
|
|
|
|
New gates to be fitted to Drungewick Lock
Drungewick lock was restored by the Trust volunteers, being finished
in 1991. The gates will be constructed from steel with wooden beams.
The wood is already to hand, having been given to the Trust by the
Upper Avon Canal Trust, in 1997.
| |  |
|

|
|  | |
Back-pumping of water released by using Brewhurst Lock has been in operation since early 1997. Back-pumping was also successfully installed by apprentices under training at Baldwin's Knob Lock in the summer of 1997.
|
|
|
|
A Back-pump for Drungewick Lock
A water abstraction licence from the river Arun will allow water
to be pumped into the canal above the Drungewick Lock. A second
pump will return water from below the lock to the pound above it
so reducing the water burden on the system when used by boats. Preparatory work has already started under the Horsham Green Health scheme.
|
|
[photos: John Wood, Arthur Dungate]
BACK
|
Last updated July 2001
|
|