model of aqueduct (3K)
Restoration
Drungewick Update

  AUGUST 2001  

 

Six months ago the Wey & Arun Canal Trust was able to report completion of the Drungewick Lane Canal Bridge by the contractors, Messrs Geoffrey Osborne of Chichester.

We indicated to you at that time that we hoped that it could be opened formally on 10 May 2001 by Sir Neil Cossons OBE, Chairman of both English Heritage and The Waterways Trust.

Little did we know that Foot and Mouth Disease (FMD) precautions were to come into force within a couple of weeks and then persist right through into the summer. Under these circumstances the Opening Ceremony had to be deferred until September, but we are very happy to report that Sir Neil is now able to join us for the event on Thursday 20 September.

Sir Neil is scheduled to arrive at Drungewick Lane on board the Trust's trip boat Zachariah Keppel in time to open the waterway below the new bridge at noon, and the Trust's Directors hope that as many as possible of those who enabled the new bridge to be built will come along to the Drungewick Lane site on 20 September to join the celebrations. Please feel free (subject to the weather!) to bring a picnic or other refreshments and enjoy this landmark in the continuing restoration of "London’s Lost Route to the Sea".

Please note that for safety reasons the Police expect to close Drungewick Lane for about an hour from 11.45 am, so we suggest that visitors to the event should come early in order to park and find a good vantage point.

The Missing Link
As mentioned before, the new Bridge represents only Phase 1 of the three part Loxwood Link Extension Project. Phase 2 has been termed The Missing Link because it involves extending the banks of the canal by some 75 yards from the present terminus at the Drungewick winding hole to the point where we are required to build a Heavy Plant Crossing. This crossing is needed to allow such plant to reach the Environment Agency’s Gauging Station on the River Lox once the canal is rebuilt and in water at this point.

 

  Heavy plant crossing (9K)

The crossing comprises two reinforced concrete abutments some 13 feet apart, one on each side of the canal, which support reinforced concrete planks thus forming a temporary bridge. The planks will be lifted into place by the Environment Agency as and when required, leaving the waterway clear for traffic at other times.

 

 

Additionally, provision is being made for stop planks to be inserted at the western (Loxwood) side of the abutments to allow the neighbouring sections of the canal to be drained for maintenance etc as and when required.

Lottery funding for The Missing Link
We are delighted to report that for the first time in the canal's restoration, the Trust has received Lottery funding which will cover most of the cost of Phase 2 of the LLEP Project. The Countryside Agency, which administers the Local Heritage Initiative in partnership with the Heritage Lottery Fund and the Nationwide Building Society’s Community Award, has agreed to make available £20,000 towards the estimated total cost of around £25,000 for Phase 2.

This grant was conditional on a number of schools taking part in a competition based on learning about the canal’s history and its effect on the local environment, and so far seven schools have indicated their intention to become involved. Study Projects have already been completed by Loxwood School and St Catherine’s School, Bramley and show an incredibly high standard of work and knowledge of the subject.

This educational opportunity arose from the generous funding by P&O Stena Line of a glossy booklet about the canal which was coupled with a CD-ROM. Copies may be obtained from the Trust’s Office for £15.00 (inc. p&p). Additionally, P&O Stena Line has provided gifts for all the children taking part, and a number of Car and Family Tickets to France for the teachers of the winning classes. The Project complies with the Key Stage 2 curriculum and the Trust would be very happy to provide further details to any other schools interested in taking part.

Rapid Progress
Even though this is turning into one of our damper summers, following that terribly wet winter, work on Phase 2 is going ahead very rapidly. This work is being undertaken almost entirely by WACT’s volunteers with only a very limited amount of professional assistance. The extension of the canal’s banks has been completed and the abutments for the Heavy Plant Crossing are in place, the planks being expected on site any time now. The aim is to complete the Phase 2 work before the Opening of the waterway underneath the Bridge on 20 September.

Slipway
At the same time as Phase 2 is being progressed, the Trust had hoped to build a new slipway into the winding hole which marks the present terminus of the canal, coupled with an approach road to enable it to be accessed from Drungewick Lane. The slipway is needed to allow Zachariah Keppel and other boats to be hauled up for inspections and maintenance, as well as to permit visiting boats to be launched onto the canal whenever required - for example for the Trust’s annual Small Boat Rally.

The slipway does not actually form part of Phase 2 of the Loxwood Link Extension Project, even though it is happening at a neighbouring site, and therefore it has to be funded separately. The estimated cost is about £20,000, of which we have already raised some 75%. The balance of around £5,000 is now being sought from several prospective donors.

Because work is continuing on Phase 2 of the LLEP to date the Trust has effected only basic clearance of the slipway and its approach road. However, it is considered that this project can be undertaken during the winter months if necessary, and those concerned are confident of completing the construction by the Spring of 2002.

What About That Aqueduct?
This is very much in the thoughts of the Trust’s Directors because building it is the only way to achieve a through waterway link to the South. Like the bridge, the aqueduct will have to be built by contractors because, while WACT’s members have the necessary skills, they cannot devote sufficient time to the job to get it finished in the limited period of dry weather - should that ever occur! All the necessary Planning and other Permissions have been obtained - all that we need now is the money!

The latest estimate is that the Aqueduct will cost close to £400,000. We have already raised, or identified the source of, over 40% of this amount. Further, earlier this month WACT submitted an application to the Heritage Lottery Fund for major funding to support this project. Of course neither the good start which has been made to this fundraising nor the hope of Lottery Funding should allow us to slacken our efforts to raise money because if the Lottery application is successful then a further £240,000 has been provisionally estimated as the amount needed to reopen the full 6 miles of waterway from Loxwood High Street to the A272 at Newbridge.

For any further information please contact -

 

BACK

Last updated September 2001